Will the Cabinet Secretary provide the latest timetable for all local planning authorities in Wales to prepare local development plans?
Answer
Answered by Cabinet Secretary for Economy, Energy and Planning
The below table sets out the key stages for Local Development Plan (LDP) progress in Wales as provided in each Local Planning Authorities (LPAs) latest Delivery Agreement (DA), including revisions, as of 9th February 2026.
LPA
Latest Delivery Agreement
Preferred Strategy
Deposit Plan
Submission
Adoption
Bannau Brycheiniog NPA – 2nd RP
DA Awaited
Blaenau Gwent - RP
July 2024
April 2025
Jan 2026
Oct 2026
Bridgend – 2nd RP
Due March 2028
Caerphilly - RP
Oct 2024
Feb 2025
Feb 2026
Nov 2026
Aug 2027
Cardiff - RP
Feb 2025
March 2025
Jan 2026
Dec 2026
Carmarthenshire - RP
Jan 2024
June 2024
Summer 2026
Ceredigion - RP
June 2018
July 2019
June 2020
Dec 2020
Dec 2021
Conwy - RP
Dec 2025
Jan 2026
Nov 2026
Oct 2027
Denbighshire - RP
Dec 2022
Sept 2023
May 2024
Sept 2025
Eryri NPA – 2nd RP
Sept 2025
Feb 2027
Nov 2027
May 2028
May 2029
Flintshire - RP
Due Jan 2027
Gwynedd – RP
March 2024
April 2025
Jan 2026
Sept 2026
Oct 2027
Merthyr Tydfil – 2nd RP
Awaiting DA
Monmouthshire - RP
Oct 2024
Jan 2023
Dec 2024
Nov 2025
Nov 2026
Neath Port Talbot - RP
Oct 2023
Dec 2024
Dec 2025
June 2026
April 2027
Newport - RP
Jan 2023
Nov 2023
Dec 2024
May 2025
Feb 2026
Pembrokeshire CC - RP
July 2024
Oct 2024
June 2025
May 2026
Pembrokeshire Coast NPA – 2nd RP
Dec 2025
March 2027
May 2028
Oct 2028
Nov 2029
Powys - RP
July 2024
Oct 2024
Nov 2025
Sept 2026
Sept 2027
Rhondda Cynon Taff - RP
July 2023
Feb 2024
Feb 2025
June 2025
May 2026
Swansea - RP
Feb 2025
April 2025
June 2026
Feb 2027
Dec 2027
Torfaen - RP
Nov 2024
Dec 2025
Dec 2026
Jan 2028
Dec 2028
Vale of Glamorgan - RP
Jan 2026
Feb 2026
Nov 2026
Sept 2027
Wrexham
Dec 2018
Unadopted
Ynys Mon - RP
Oct 2024
Jan 2026
Oct 2026
June 2027
May 2028
Note: All submission and adoption dates after February 2026 are indicative, assuming a plan will be submitted and can be adopted. RP stands for Replacement Plan. 2nd RP stands for Second Replacement Plan.