Can I add something, unless you want to go first, Fiona? There are two things. One is—I completely agree with Simon—that all of those cases, with different applications, different local authorities, are true, and it's very hard to say, because it isn't—. Even recently, with a local authority—we obviously won't name them—we couldn't submit a SAB application—it sits outside of planning—because they had nobody in their department to take the fee to validate it for a whole month. That's a site for social housing that was in this year's delivery and which is now in next year's, purely because—well, I say 'purely'; I'm simplifying it—. That was a key reason, and there's nothing we could have done about that, but that's a separate discussion.
What I do want to raise though, which I think is important, is, in today's world, I think we just all need to be realistic with the actual timescale to get planning, regardless of the changes. The process isn't an eight-week planning application. The process is this: an initial pre-application, then a second pre-app, which you're encouraged to do, otherwise your application might be declined at planning. Both of those can take two to three months each, but more like three to four months each. Then you've got, in most cases, a pre-application consultation, which is the public consultation. It's a month's process, before you submit an application. So, you're already seven months in, which nobody sees. Then you're at the planning application, which might, if you're lucky, take eight weeks, but most of the time it takes four months, and, to be honest, four months most people could live with. After the planning application, you've then got committee most of the time, especially with social and affordable housing, because they always get public backlash, they're always contentious and they always get called in to committee. Again, I'm oversimplifying here. Then you might need a site visit, and that's a two-month process. After you've finally, hopefully, got consent at committee, you only then can start the 106 process, which in itself can take months. Drafting a section 106, which I raised in the affordable housing taskforce and last year, still can take months—and it's a document; there's no standardisation of it—even for small schemes.
After the section 106 is finally drafted and signed, only then is the decision notice released, and after the decision notice is released, you've got a six-week judicial review period, and no-one will really do anything until that period lapses. And whilst that's lapsing, you can only then start discharging your pre-commencement conditions, under which you legally cannot start construction until they're discharged. So, all in all, we are not talking about an eight-week timescale, which a lot of people do and refer to. The system is set up, at the moment, for planning to take, from start to finish, more like a year and a half. That is it.